Gradeworks

Working with work blocks

Create, configure, and manage work blocks — the individual units of work that make up your project schedule.

A work block is a single piece of scheduled work — "Grade parking lot", "Install storm drain", "Pave south lane." Each block has a duration, crew assignment, and date range. Blocks are the atoms of your project schedule. Everything else — dependencies, critical path, recast, dispatch — operates on blocks.

Creating a work block

  1. Open a project and go to the Timeline tab
  2. Click Add Block (or double-click on the timeline)
  3. Enter a descriptive name — be specific enough that the foreman knows exactly what to do
  4. Set the duration in working days
  5. Assign a crew from the dropdown (shows available crews by type)
  6. Set the start date (or let it cascade from dependencies)
  7. Click Save — the block appears on the timeline

Block properties

  • Name — what the work is
  • Duration — how many working days (respects your work week and holiday calendar)
  • Crew — which crew performs the work
  • Start/End date — when the work is scheduled (can be pinned or calculated)
  • Status — Not Started, In Progress, Completed
  • Completion % — tracked manually or via field app check-ins
  • Notes — instructions, materials needed, access information for the crew
  • Equipment — specific equipment assigned to this block

Editing blocks

Click a block on the timeline to open its detail panel. Edit any property directly. Drag the block to move it to a different date. Drag the right edge to change duration. Changes trigger recast if dependencies or constraints are affected — the rest of the schedule adjusts automatically.

Completion tracking

Track block completion by updating the percentage manually in the detail panel, or let the field app update it based on foreman sign-off. Completed blocks turn a muted color on the timeline. The project's overall completion percentage is calculated from its blocks — each block contributes proportionally based on its duration.

Pro tip
Write block notes as if you're briefing the foreman who's never been to the site. Include access directions, material delivery timing, coordination with other crews, and anything unusual about the site. Notes that say 'Grade lot' don't help — notes that say 'Grade lot, access from south gate only, water main runs along east boundary — keep 10ft clear' prevent problems.

Was this helpful?

Related articles

Still need help?

Our team typically responds within 4 business hours.

Contact support